The U.S. Army Corps of Engineers (USACE) depends on federal funding to complete its work on our levee project. When the project does not receive adequate funding, the USACE must stop work on the project until the next federal budget is passed. The project is now over three years behind its original schedule due to inadequate federal funding.
For example: In 2007, the USACE received $1.0 million of the $1.6 million that was requested. As a result, the Corps ran out of funds in July, and was not able to complete the Environmental Impact Study/Environmental Impact Report (EIS/EIR) in January 2008, as planned. Inadequate funding has delayed the EIS/EIR by yet another six months.
During this time, the USACE plans to complete the environmental review and final design. Once this has been completed, the community will be able to implement a local funding mechanism and begin cost-sharing on the project. Given the very unique and valuable 75% federal cost-share of the total project cost, the local funding mechanism will be required to fund the remaining 25% of the total project cost.
In order to keep the project on schedule and complete the final project design, the local sponsors are developing strategies to increase federal funding, and to supplement insufficient federal funding with alternative funding sources. These strategies include: